Dallas targets spring 2029 for long delayed Joppa pedestrian bridge

City officials say the pedestrian bridge project in Dallas has a new completion timeline of spring 2029 following a recent agreement with Union Pacific.

View of the Margaret Hunt Hill Bridge with a train passing underneath in Dallas, Texas.
Photo by Danny Meneses on Pexels
Ask AI about this:ChatGPTClaudePerplexityGoogle AI

The Dallas City Council authorized an estimated $523,000 agreement with Union Pacific for a pedestrian crossing over railroad tracks near Linfield Road in the Joppa neighborhood. City officials said the project now targets a completion date in spring 2029. The agreement sets how much the railroad will charge the city to oversee and coordinate construction.

Residents in the historic southern Dallas neighborhood have waited years for a safe pedestrian route. The community is zoned for industrial use and is surrounded by railroad lines, major highways, and the Trinity River, which leaves very few options for getting in and out of the area.

Without that safe crossing, residents have had to walk beside speeding vehicles on narrow roads or squeeze between stationary train cars to reach their homes.

Residents previously voted in 2018 to allow Union Pacific to permanently close a surface pedestrian crossing on the condition that a dedicated pedestrian bridge would replace it. Without that safe crossing, residents have had to walk beside speeding vehicles on narrow roads or squeeze between stationary train cars to reach their homes.

Financial backing for the project gathered momentum when regional transportation planners approved funding in 2019. Construction timelines shifted repeatedly from an initial completion target of 2023 to a planned start in 2024 before settling on the current 2029 completion window.

The city transportation department estimated the overall cost of the pedestrian bridge at $10 million. The department said the extended timeline is due to extensive coordination required with the railroad company, the Texas Department of Transportation, and the North Central Texas Council of Governments.

City officials announced that the newly approved contract grants necessary right-of-way permissions for the construction work. Transportation department representatives said that engineering and coordination phases are continuing toward the spring 2029 opening.

Sources
  • Hoodline: Joppa Pedestrian Bridge Delay: Dallas Targets Spring 2029
  • Dallas News: Dallas' Joppa neighborhood closer to long-promised pedestrian bridge

Watch: #Dallas City Hall faces growing revolt over who gets to shape the city

From The Dallas Morning News on YouTube

Questions readers ask

When is the Joppa pedestrian bridge expected to open?

City officials said the project now targets a completion date in spring 2029. Timelines previously shifted from an initial completion target of 2023 and a planned start in 2024.

Why has the pedestrian bridge project been delayed?

The city transportation department said the extended timeline is due to extensive coordination required with the railroad company, the Texas Department of Transportation, and the North Central Texas Council of Governments.

How much will the pedestrian bridge project cost?

The city transportation department estimated the overall cost of the pedestrian bridge at $10 million. This includes an estimated $523,000 agreement with Union Pacific to oversee and coordinate construction.

Why does the Joppa neighborhood need this bridge?

Residents voted in 2018 to let Union Pacific close a surface crossing on the condition that a bridge would replace it. Without it, residents have had to walk beside speeding vehicles on narrow roads or squeeze between stationary train cars.

Quick quiz

How closely did you read? Pick an answer.

1. What is the new target completion window for the Joppa pedestrian bridge?
2. What is the estimated overall cost of the pedestrian bridge project?
3. Which railroad company did the Dallas City Council authorize an agreement with?

More Local

Dallas Has $32.5 Million in Police Academy Funding, Seeks $82 Million From Voters

Dallas has accepted donations and grants for a police training facility but is still seeking voter approval for $82 million toward a police academy.

Texas Supreme Court to Hear Dallas Short-Term Rental Case Amid Local Development and Election Updates

The Texas Supreme Court is set to hear arguments on Dallas' short-term rental ban ordinance as officials review Sand Branch fire protection, Oak Cliff transit plans, and regional development proposals.

Missing Teen Alert, Regional Water Pipeline Proposal and Suburban Downtown Investments Top Dallas News

Dallas police are seeking the public's help to find a missing 13-year-old girl, while regional reports highlight suburban downtown investments, an Arkansas water pipeline proposal, and upcoming rain.

Luis Herrera

Luis HerreraBusiness writer

Luis writes about North Texas business, property and jobs.